Production Planning
Production planning determines what products should be produced, how many units should be produced, and when production should occur while considering forecast demand, inventory, workforce, materials, machine capacity, and production lead times. A basic production balance is Production = Demand + Desired Ending Inventory - Beginning Inventory. This relationship connects production decisions to inventory levels across planning periods. Short-term planning may use a Master Production Schedule (MPS) to specify when finished products should be produced, while aggregate planning considers product families, workforce levels, inventory, overtime, subcontracting, and capacity over a longer planning horizon. A production plan must account for available capacity: required production hours cannot exceed the capacity provided by available machines and labor unless overtime, additional shifts, subcontracting, or other capacity actions are introduced. Two common aggregate-planning strategies are level production, which keeps the production rate relatively stable while inventory absorbs demand variation, and chase production, which changes production capacity or output to follow demand more closely. Inventory provides a buffer between production and demand but creates holding costs and may become obsolete. Safety stock can be maintained to protect against demand or supply uncertainty. Material requirements must also be synchronized with production through bills of material, inventory records, and lead times. A feasible production plan satisfies demand and inventory requirements without violating capacity, material, workforce, or policy constraints. Production planning is therefore a time-phased resource allocation problem rather than simply a forecast of how many units customers will buy.
Knowledge Check
1.What is the primary purpose of production planning?
2.A company expects demand of 800 units, wants 150 units of ending inventory, and starts the period with 200 units. How many units should it produce?
3.If beginning inventory is 300 units, production is 900 units, and demand is 1,000 units, what is the ending inventory?
4.What is the main purpose of a Master Production Schedule (MPS)?
5.A machine can operate 8 hours per day for 5 days, with one machine available. What is its theoretical weekly capacity?
6.A product requires 0.5 machine-hours per unit. If 120 machine-hours are available, what is the maximum production quantity based only on this capacity?
7.What is the main characteristic of a level production strategy?
8.What is the main characteristic of a chase production strategy?
9.Why can holding large inventories be undesirable even when they protect against stockouts?
10.What is the purpose of safety stock in production planning?
11.A production plan requires 500 machine-hours, but only 420 hours are available. What does this indicate?
12.What is the role of a bill of materials (BOM) in production planning?
13.Why are lead times important in production planning?
14.A company produces 1,000 units per month while monthly demand is 800 units. If no other inventory changes occur, what happens to inventory during the month?
15.Which situation most directly suggests that a production plan should be revised?
16.What is a major trade-off between a level production strategy and a chase strategy?